Wind Energy Stagnation in Massachusetts and a Path Forward15 Jan

From 2001 until present time, wind turbine installation in Massachusetts (MA) has proceeded at a glacial pace. This fact raises serious issues for public and private policy analysts in MA. For example: During this 10 year period, only 38 MW of wind turbines has been installed with a potential of 1000 MW. (See Additional Wind […]
blog

Wind Energy, Offshore Case – Business Development Issues28 Apr

Cape Wind Project: Started in 2001, the Cape Wind project is an offshore wind farm that will consists of 131 turbines situated within a 24 square mile area on the south coast of Cape Cod. The peak nameplate generating capacity is 454 megawatts (MW) and will deliver 170 MW on average due to the intermittent […]
blog

Wind Energy, Offshore Case – Subsidies, Contribution to Massachusetts Electricity Generation26 Apr

Cape Wind Project: Started in 2001, the Cape Wind project is an offshore wind farm that will consists of 131 turbines situated within a 24 square mile area on the south coast of Cape Cod. The peak nameplate generating capacity is 454 megawatts (MW) and will deliver 170 MW on average due to the intermittent […]
blog

Wind Energy, Offshore Case – High Cost of Electricity20 Apr

Cape Wind Project: Started in 2001, the Cape Wind project is an offshore wind farm that will consists of 131 turbines situated within a 24 square mile area on the south coast of Cape Cod. The peak nameplate generating capacity is 454 megawatts (MW) and will deliver 170 MW on average due to the intermittent […]
blog

Wind Energy, Offshore Case—Development Time, Capital Cost18 Apr

Cape Wind Project: Started in 2001, the Cape Wind project is an offshore wind farm that will consists of 131 turbines situated within a 24 square mile area on the south coast of Cape Cod. The peak nameplate generating capacity is 454 megawatts (MW) and will deliver 170 MW on average due to the intermittent […]

About Dr. Everson

Prior to forming this SBIR consultant practice, Dr. Jeffrey Everson was director of business development for QinetiQ North America’s Technology Solutions Group (previously Foster-Miller, Inc.).

Dr. Everson has won and been the principal investigator for several SBIR programs, including a Phase I program for NASA, a Phase I project for the U.S. Air Force, and Phase I and II contracts from the U.S. Department of Transportation. For the Phase II program, he received a Tibbetts Award for exemplifying the best in SBIR achievement.

Previously Dr. Everson held senior scientist positions at Battelle Memorial Institute, The Analytic Sciences Corporation (TASC), Honeywell Electro Optics Systems Division, and Itek Optical Systems Division.

He holds a PhD in physics from Boston College and a MS/BS in physics from Northeastern University.

Contact

For more information about how JHEverson Consulting can help your company with its SBIR and STTR proposals, please contact Jeff Everson.

JHEverson Consulting is based in the Boston area but consults for clients throughout North America. It also is supported by affiliated consultants.